Xay Dung Viet Phu

Site records

Checking renovation work before anyone signs it off

Four procedures, written the way a supervisor runs them: a straight edge on plaster, a moisture reading on screed, a tapping rod on tiles, and a written register for every open item.

Section drawing of a plastered wall checked with a straight edge next to a tile setting out grid and a floor build up of slab, membrane, insulation, screed and tile
The three checks that catch most renovation defects: wall flatness, tile setting out, floor build up.

01.The four procedures

Each page below covers one trade handover. Every page gives the measuring method, the number the work has to meet, and the wording to use when the work fails. Read the page before the inspection, not after the argument starts.

02.Headline numbers

The table below collects the figures quoted most often during handover. Each figure is a working limit used on fit out jobs, and the contract specification overrides every line of the table when the two disagree.

Table 1. Acceptance figures used at handover

CheckInstrumentWorking limitPage
Plaster flatness, general standard2 m straight edge5 mm gapPlaster
Plaster flatness, high standard2 m straight edge3 mm gapPlaster
Abrupt change in a plaster surface300 mm straight edge2 mm stepPlaster
Screed flatness under ceramic tile2 m straight edge5 mm gapScreed
Screed moisture before ceramic tileSurface hygrometer75 percent RHScreed
Tile lippage, joints up to 6 mmFeeler gauge or dial gauge1 mmTiling
Adhesive coverage, wet areas and floorsLift one tile95 percent bedTiling
Perimeter movement joint at wallsTape6 mm to 10 mmTiling

Working limits collected from fit out practice. Confirm every value against the project specification before rejecting work.

Kit for a handover walk

  • 2 m aluminium straight edge, checked against a known flat surface every month
  • 300 mm straight edge for local steps and reveals
  • Feeler gauges from 0.5 mm to 5 mm
  • Rechargeable work lamp for raking light across walls and floors
  • Nylon tipped tapping rod for hollow tiles and hollow render
  • Surface hygrometer with sealed insulated boxes, one per 200 square metres
  • Camera with a date stamp and a numbered marker card
  • Printed register with room numbers already filled in

03.How these pages are written

Every figure on this site carries a measuring method next to the number, because a tolerance without a method is unenforceable. A gap of 4 mm means nothing until the length of the straight edge is stated. A moisture reading means nothing until the depth and the sealing time are stated. The about page explains the recording habits behind the four procedures.